US3779021A US00212217A US3779021DA US3779021A US 3779021 A US3779021 A US 3779021A US 00212217 A US00212217 A US 00212217A US 3779021D A US3779021D A US 3779021DA US 3779021 A US3779021 A US 3779021A
Authority
US
United States
Prior art keywords
mold
pipe
concrete
poured
headwall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US00212217A
Inventor
R Green
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Application granted granted Critical
Publication of US3779021A publication Critical patent/US3779021A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • E01F5/005Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/46Foundations for supply conduits or other canals

Definitions

  • headwall refers to the reinforced concrete structure which supports one end of a large pipe and retains earth fill onone side. Instead of building concrete forms on the site the headwall is poured into a form made from two identical lightweight plastic concave sections which are made to shape and size by vacuum forming identical plastic sheets placed back-to-back to produce the mold which is a shell having the two sections attached together by plastic strips or the like. Each concave plastic section is vacuum formed with an intricate shape to produce an outwardly extending base and an upright retaining wall which may have a circular or oval-shaped hole passing through the walls to accommodate the drainage pipe. The plastic walls around the hole may be weak so as to distort around the pipe or may be split.
  • the completed form has openings at the top through which concrete is poured. The bottom may be open so that concrete can come into contact with the irregular terrain or soil.
  • Field of the Invention Headwall construction for drainage pipe and the like; reinforced concrete construction. Prefabricated forms for concrete and the like.
  • the forms are shored-up with timbers, boards and stakes which have been driven into the ground;
  • step 6. only after step 6. above can the backfilling be done to cover-up the remainingexposed drainage pipe to the headwall;
  • the present method and apparatus permits the forming of head walls and filling of earth to be coordinated in an improved and more efficient manner and sequence. In some instances this method can eliminate the steps 2, 3, 4, S, 6 and '7 previously mentioned.
  • this method can eliminate the steps 2, 3, 4, S, 6 and '7 previously mentioned.
  • the present headwall construction there is no manual building or preparation of forms but rather two identical prefabricated half-shells or molded sections are placed back-to-back to form a hollow headwall form which is filled with concrete from openings in the top after the pipe is inserted through a hole in the middle.
  • the purpose of the present headwall form is to provide a simple, easy and less expensive way of forming a concrete headwall around the end of a drainage pipe and to facilitate the pouring of concrete by controlling, directing and confining wet concrete to a predetermined configuration and shape.
  • prefabricated half-shellsor form sections are combined simply by fastening together leaving an open base in communication with the ground. This eliminates all of the manual construction of concrete formsand furthermore installation can be done by ordinary day laborers instead of carpenters.
  • Rigidity is obtained by transforming a thin sheet I into an intricate shape of ribs, channels, flanges and tubes to create stiffness so that the unit can support wet concrete pressure and other forces while maintaining the desired shape. No shoring is required.
  • the position, placement and size of the. ribs, channels, flanges or tubes may be predetermined so as to minimize deflection wherever not wanted. Molded flanges may be bonded together.
  • the walls of the form sections may be made thinner or thicker wherever desired and in the area of a center hole where the drainage is inserted the shell may be made thin or even frangible to provide deflections for two reasons: i
  • Installation is quickand easy and does not materially delay back filling of earth which may be done as soon as the concrete has set and without removing the present form which may be left in place without deterioration.
  • the mold is smooth and no finish is required.
  • the mold is easily installed and there are openings whereby reinforcing rods may be inserted or for other purposes.
  • FIG. 1 is a perspective view of a typical molded plastic shell which is one half of the completed form made from two of these shells.
  • FIG. 2 is a perspective view of two of the half shells placed back-to-back to make the completed form which is receiving concrete through the top.
  • FIG. 3 is a cross-sectional view taken substantially along lines 3-3 in FIG. 2.
  • FIG. 4 is a cross-sectional view taken substantially along lines 4-4 in FIG. 3.
  • FIG. 5 is a cross-sectional view taken substantially along lines 5-5 in FIG. 3.
  • FIG. 6 is a cross-sectional view taken substantially along lines 6-6 in FIG. 3.
  • FIG. 7 is a partial perspective view of a modified form of the interior of the center opening.
  • FIG. 8 is a bottom view of the completed form shown in FIG. 2 with a portion thereof broken away.
  • the completed form is made up of two concave sections each designated generally by reference numeral 10 and each of which may be manufactured from thin plastic sheets that are molded and stretched to a specific configuration to produce the shell together with various integral stiffening means such as flanges, bulges and channels at certain predetermined locations.
  • Each section 10 may be manufactured from any plastic having sufficient strength from its inherent quality as well as rigidity from design configuration to resist loads imposed upon it from inside by freshly poured concrete.
  • the plastic may be of the type ABS, polyethylene, polystyrene, or polypropelene which can be molded into any intricate shape to produce the desired shell.
  • the shell or half form 10 may be manufactured by the well known thermoforming process, commonly known as vacuum forming, by forming a plastic sheet into the shell 10 which in turn is attached back-to-back to another identical shell.
  • the completed form is made up of two prefab half-forms, also called shells or half-sections 10, placed back-to-back in the manner shown in FIG. 2 into a completed mold used as a form and designated generally by reference numeral 12.
  • the completed headwall form 12 includes a center pipe opening 14 through which a typical concrete pipe 41 or corrugated metal pipe is inserted.
  • Each shell 10 comprises a concave vertical section designated generally by reference numeral 16 having end walls 17 and a concave base or horizontal section designated generally by reference numeral 18 with end walls 19 which are integrally formed as one complete unit.
  • a flat peripheral flange 20 extends all around the margin or edge of the shell 10.
  • the peripheral flange 20 on one shell 10 in FIG. 2 is placed against and super-imposed on an identical flange 20 on the other identical back-to-back section 10 creating a complete substantially hollow form 12 which is hollow inside until filled with concrete 26 from a pouring spout 29 or any other source.
  • the concrete 26 is poured through a top wall 27 having openings 28 created by matching cut-out openings 30 on one shell 10 with the identical cut-out sections 30 on the other identical shell 10.
  • the base 18 is molded with a plurality of longitudinal cavities 34 which create concrete ribs 35 in the base after the concrete 26 is poured therein.
  • the ribs 35 thereby formed provide strengthening means in a concrete base 36 which is formed inside of the base 18 and the bulges 34 provide the ribs 35 in the shell 18 in such a way as to strengthen the mold and prevent abnormal deformation during pouring and the like.
  • the two mold sections 10 are placed back-to-back as mentioned previously and in the manner seen in FIG. 2 are attached by means of straps 38 of plastic or other material attached across the bottom from flange 20 on one side to flange 20 on the other. Straps 38 may be plastic strips which are attached in place by solvents, plastic adhesive, plastic welding or any other suitable means such as ethylene dichloride, epoxy glue, stapling or otherwise.
  • the center opening 14 has a peripheral thin-wall construction 40 which bulges under the pressure from the poured concrete 26 and tightly squeezes around a concrete pipe 41 placed therein. After the two sections 10 are assembled, the pipe is inserted in the opening 14 and concrete 26 is poured in place.
  • the wall 42 of the form is formed with a series of interrupted projecting flanges 44 separated from each other by slits and openings 46 which allow the concrete 26 to drain around the pipe inserted in the opening.
  • the flanges 44 occupy a position almost perpendicular to the wall 42 and are pushed and displaced by the drainage pipe to practically a horizontal position. Flanges 44 displaced by a pipe help align, center and retain the form 12 in place until after the concrete is poured and set.
  • supporting flanges can be made as an integral part of the mold by the contouring and shaping of the bottom straps 38 and sides of the mold 10 or by horizontal projections or plastic pins (not shown) inserted where needed inside the mold on which the rods when placed are held in proper position and alignment. Additional plastic straps 38 may be placed and attached to the base wherever desired to prevent pronounced spreading and distortion of the base dimension. Such straps 38 will also serve the function of reducing the upper force of the wet concrete on the mold which would cause the mold base to separate from contact with the ground.
  • the thickness of the walls of the shell 10 can be controlled and governed by the mold process whereby stretching and distortion can be predetermined either to permit it to take place if desired or to prevent it from taking place if not desired.
  • the wall 40 may be made thin so that it will bulge and stretch under the weight of the concrete to tightly squeeze around the concrete pipe.
  • bleed holes 54 may be placed through the shell 10 at critical locations to allow possible and trapped air to escape and to give positive indication that all voids are filled with concrete.
  • the positive indication will be in the form of the appearance of concrete at the bleed holes 54.
  • the shell configuration 10 is such that the placement of the ribs 34, channels and other tubes wherever needed in conjunction with large corner radius and fillets will control the flow and direction of the concrete during pour. This tends to minimize air entrapment thereby precluding the necessity of tapping and packing the mold or vibrating the wet concrete. It also helps to provide free concrete casting.

Abstract

The expression ''''headwall'''' refers to the reinforced concrete structure which supports one end of a large pipe and retains earth fill on one side. Instead of building concrete forms on the site the headwall is poured into a form made from two identical lightweight plastic concave sections which are made to shape and size by vacuum forming identical plastic sheets placed back-toback to produce the mold which is a shell having the two sections attached together by plastic strips or the like. Each concave plastic section is vacuum formed with an intricate shape to produce an outwardly extending base and an upright retaining wall which may have a circular or oval-shaped hole passing through the walls to accommodate the drainage pipe. The plastic walls around the hole may be weak so as to distort around the pipe or may be split. The completed form has openings at the top through which concrete is poured. The bottom may be open so that concrete can come into contact with the irregular terrain or soil.

Description

United States Patent [1 1 Green METHOD OF MAKING A HEADWALL [76] lnventor: Robert H. Green, 550 High Point Ln., NE, Atlanta, Ga. 30342 [22] Filed: Dec. 27, 1971 [21] Appl. N0.: 212,217
[52] US. Cl 6l/16, 61/17, 248/54 [51] Int. Cl E02d 5/20 [58] Field of Search 52/380, 382, 439;
Primary ExaminerMervin Stein Assistant Examiner-David H. Corbin Att0rney-Patrick F. Henry [451 Dec. 18, 1973 5 7 ABSTRACT The expression headwall refers to the reinforced concrete structure which supports one end of a large pipe and retains earth fill onone side. Instead of building concrete forms on the site the headwall is poured into a form made from two identical lightweight plastic concave sections which are made to shape and size by vacuum forming identical plastic sheets placed back-to-back to produce the mold which is a shell having the two sections attached together by plastic strips or the like. Each concave plastic section is vacuum formed with an intricate shape to produce an outwardly extending base and an upright retaining wall which may have a circular or oval-shaped hole passing through the walls to accommodate the drainage pipe. The plastic walls around the hole may be weak so as to distort around the pipe or may be split. The completed form has openings at the top through which concrete is poured. The bottom may be open so that concrete can come into contact with the irregular terrain or soil.
5 Claims, 8 Drawing Figures cat/79,021
PATENTED DEC 18 I575 R RT E G EE wmwrw i fl ATTOR 5y WNW I EO/ 1 METHOD OF MAKING A HEADWALL BACKGROUND OF THE INVENTION 1. Field of the Invention Headwall construction for drainage pipe and the like; reinforced concrete construction. Prefabricated forms for concrete and the like.
2. Description of the Prior Art The usual headwall construction involves the manual preparation of forms made from wood, plywood and other materials built at the location and stripped away after construction. The form is primarily temporary and may be removed after construction. There is a certain amount of expense involved for carpentry and other trades in the manual construction of forms. A lot of time is consumed in preparing and constructing the form and completing the work. The typical steps are as follows:
1. wooden forms are constructed and assembled around the pipe end which has not been covered with earth. Pieces of heavy wooden planks and plywood sections are nailed together to form a concrete mold;
2. the forms are shored-up with timbers, boards and stakes which have been driven into the ground;
3. paper or similar soft material is stuffed around the pipe and the wooden form to prevent concrete seepage and loss. There is a pronounced gap in this area as the wooden forms cannot accurately be fitted within the time and skill permitted. Also, there is a tolerance and variation in pipe diameter due to normal allowances in pipe standards;
4. the forms are greased to facilitate removal;
5. during pouring the wet concrete needs to be vibrated to remove air voids;
6. after the poured concrete has become hard, the wood forms have to be removed since wood will deteriorate. State road departments require the forms to be removed; I I a 7. the surface of the poured concrete should be smoothed and rubbed to remove imperfections left after form removal;
8. only after step 6. above can the backfilling be done to cover-up the remainingexposed drainage pipe to the headwall;
The above noted operations requireworkmen to attend and leave the work site three times and the use of semi-skilled labor is costly. Concrete finishing is also costly;
The present method and apparatus permits the forming of head walls and filling of earth to be coordinated in an improved and more efficient manner and sequence. In some instances this method can eliminate the steps 2, 3, 4, S, 6 and '7 previously mentioned. In the present headwall construction there is no manual building or preparation of forms but rather two identical prefabricated half-shells or molded sections are placed back-to-back to form a hollow headwall form which is filled with concrete from openings in the top after the pipe is inserted through a hole in the middle.
SUMMARY OF THE INVENTION The purpose of the present headwall form is to provide a simple, easy and less expensive way of forming a concrete headwall around the end of a drainage pipe and to facilitate the pouring of concrete by controlling, directing and confining wet concrete to a predetermined configuration and shape. Two identical concave,
prefabricated half-shellsor form sections are combined simply by fastening together leaving an open base in communication with the ground. This eliminates all of the manual construction of concrete formsand furthermore installation can be done by ordinary day laborers instead of carpenters.
Some of the advantages and features of this headwall form, which can be made by relatively thin plastic sheets, is as follows:
I. By utilizing thin plastic sheets or the like to construct the two sections or half-shells the complete form is made in an inexpensive manner and is very lightweight and can be handcarried to the site.
2. Rigidity is obtained by transforming a thin sheet I into an intricate shape of ribs, channels, flanges and tubes to create stiffness so that the unit can support wet concrete pressure and other forces while maintaining the desired shape. No shoring is required. The position, placement and size of the. ribs, channels, flanges or tubes may be predetermined so as to minimize deflection wherever not wanted. Molded flanges may be bonded together.
3. The walls of the form sections may be made thinner or thicker wherever desired and in the area of a center hole where the drainage is inserted the shell may be made thin or even frangible to provide deflections for two reasons: i
a. to provide ease of inserting the drainage into the mold prior to the pouring of concrete.
b. to allow significant deflections during and after the concrete is poured to provide for interlocking and securing. If a thin membrane is used the fluid pressure of the wet concrete will force the thin membrane shell around the circumference of the drainage pipe. If openings are used, then the wet concrete will run through the openings into contact with the pipe. In either case the center opening will be formed to the shape of the pipe and after the concrete is hardened a secure interlocking fit will have been made. The concrete flow is even and complete without tapping or vibrating.
4. Installation is quickand easy and does not materially delay back filling of earth which may be done as soon as the concrete has set and without removing the present form which may be left in place without deterioration. The mold is smooth and no finish is required.
5. It is possible to accommodate many different sizes of pipe with the same half sections because of the expansion possible inthe center opening.
6. The mold is easily installed and there are openings whereby reinforcing rods may be inserted or for other purposes.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view of a typical molded plastic shell which is one half of the completed form made from two of these shells.
FIG. 2 is a perspective view of two of the half shells placed back-to-back to make the completed form which is receiving concrete through the top.
FIG. 3 is a cross-sectional view taken substantially along lines 3-3 in FIG. 2.
FIG. 4 is a cross-sectional view taken substantially along lines 4-4 in FIG. 3.
FIG. 5 is a cross-sectional view taken substantially along lines 5-5 in FIG. 3. I
FIG. 6 is a cross-sectional view taken substantially along lines 6-6 in FIG. 3.
FIG. 7 is a partial perspective view of a modified form of the interior of the center opening.
FIG. 8 is a bottom view of the completed form shown in FIG. 2 with a portion thereof broken away.
DESCRIPTION OF A PREFERRED EMBODIMENT The completed form is made up of two concave sections each designated generally by reference numeral 10 and each of which may be manufactured from thin plastic sheets that are molded and stretched to a specific configuration to produce the shell together with various integral stiffening means such as flanges, bulges and channels at certain predetermined locations. Each section 10 may be manufactured from any plastic having sufficient strength from its inherent quality as well as rigidity from design configuration to resist loads imposed upon it from inside by freshly poured concrete. For example, the plastic may be of the type ABS, polyethylene, polystyrene, or polypropelene which can be molded into any intricate shape to produce the desired shell. The shell or half form 10 may be manufactured by the well known thermoforming process, commonly known as vacuum forming, by forming a plastic sheet into the shell 10 which in turn is attached back-to-back to another identical shell.
In the drawing, the completed form is made up of two prefab half-forms, also called shells or half-sections 10, placed back-to-back in the manner shown in FIG. 2 into a completed mold used as a form and designated generally by reference numeral 12. The completed headwall form 12 includes a center pipe opening 14 through which a typical concrete pipe 41 or corrugated metal pipe is inserted.
Each shell 10 comprises a concave vertical section designated generally by reference numeral 16 having end walls 17 and a concave base or horizontal section designated generally by reference numeral 18 with end walls 19 which are integrally formed as one complete unit. A flat peripheral flange 20 extends all around the margin or edge of the shell 10. Thus, the peripheral flange 20 on one shell 10 in FIG. 2 is placed against and super-imposed on an identical flange 20 on the other identical back-to-back section 10 creating a complete substantially hollow form 12 which is hollow inside until filled with concrete 26 from a pouring spout 29 or any other source. The concrete 26 is poured through a top wall 27 having openings 28 created by matching cut-out openings 30 on one shell 10 with the identical cut-out sections 30 on the other identical shell 10.
The base 18 is molded with a plurality of longitudinal cavities 34 which create concrete ribs 35 in the base after the concrete 26 is poured therein. The ribs 35 thereby formed provide strengthening means in a concrete base 36 which is formed inside of the base 18 and the bulges 34 provide the ribs 35 in the shell 18 in such a way as to strengthen the mold and prevent abnormal deformation during pouring and the like.
The two mold sections 10 are placed back-to-back as mentioned previously and in the manner seen in FIG. 2 are attached by means of straps 38 of plastic or other material attached across the bottom from flange 20 on one side to flange 20 on the other. Straps 38 may be plastic strips which are attached in place by solvents, plastic adhesive, plastic welding or any other suitable means such as ethylene dichloride, epoxy glue, stapling or otherwise. In one form of the invention shown in FIG. 1, the center opening 14 has a peripheral thin-wall construction 40 which bulges under the pressure from the poured concrete 26 and tightly squeezes around a concrete pipe 41 placed therein. After the two sections 10 are assembled, the pipe is inserted in the opening 14 and concrete 26 is poured in place.
In another form shown in FIG. 7, the wall 42 of the form is formed with a series of interrupted projecting flanges 44 separated from each other by slits and openings 46 which allow the concrete 26 to drain around the pipe inserted in the opening. The flanges 44 occupy a position almost perpendicular to the wall 42 and are pushed and displaced by the drainage pipe to practically a horizontal position. Flanges 44 displaced by a pipe help align, center and retain the form 12 in place until after the concrete is poured and set.
In the event reinforcing rods (not shown) should be placed within the completed mold 12 prior to pouring the concrete 26, supporting flanges can be made as an integral part of the mold by the contouring and shaping of the bottom straps 38 and sides of the mold 10 or by horizontal projections or plastic pins (not shown) inserted where needed inside the mold on which the rods when placed are held in proper position and alignment. Additional plastic straps 38 may be placed and attached to the base wherever desired to prevent pronounced spreading and distortion of the base dimension. Such straps 38 will also serve the function of reducing the upper force of the wet concrete on the mold which would cause the mold base to separate from contact with the ground.
It is worthwhile to note that the thickness of the walls of the shell 10 can be controlled and governed by the mold process whereby stretching and distortion can be predetermined either to permit it to take place if desired or to prevent it from taking place if not desired. For example, as mentioned previously the wall 40 may be made thin so that it will bulge and stretch under the weight of the concrete to tightly squeeze around the concrete pipe. I
In addition to the above noted construction, bleed holes 54 may be placed through the shell 10 at critical locations to allow possible and trapped air to escape and to give positive indication that all voids are filled with concrete. The positive indication will be in the form of the appearance of concrete at the bleed holes 54.
The shell configuration 10 is such that the placement of the ribs 34, channels and other tubes wherever needed in conjunction with large corner radius and fillets will control the flow and direction of the concrete during pour. This tends to minimize air entrapment thereby precluding the necessity of tapping and packing the mold or vibrating the wet concrete. It also helps to provide free concrete casting.
Further strength in the mold may be obtained by having the depressions 60 formed in the vertical section 16 by tapered walls 62 leading to a flat apex 64 whereby apexes 64 on one section 10 abutts the apexes on the other matching section 10 as seen in FIG. 3. The apexes are bonded to each other as are other parts of the sections 16 that touch.
While I have shown and described a particular embodiment of this invention together with at least one suggested modified form this is by way of illustration of known preferred embodiments and does not constitute any sort of limitation since there are various changes, alterations, eliminations, deviations, additions, subtractions, combinings, removals and departures which may be made in the forms disclosed and discussed without departing from the scope of my invention as defined only by a proper interpretation of the appended claims.
I claim:
1. In a method of making a headwall from poured material, including concrete, for a pipe inserted therein:
a. prefabricating a lightweight concrete mold having walls defining an opening for the pipe inserted and an open hollow interior into which the material may be poured, said mold having a base and an upright pipe supporting portion therein in open communication to receive the poured material to form a base and upright portion in said mold from concrete,
b. making openings in said mold into which the material is poured after said mold is in place,
0. placing said assembled and completed mold in place in situ over the end of said pipe and pouring the material, including concrete, into said mold allowing the material to harden and providing a means for the mold to adjust to said pipe size by means of the poured material,
d. then backfilling against said headwall leaving said mold permanently in place.
2. The method claimed in claim 1:
fabricating said mold with deformable, solid walls around said pipe supporting portion which distorts from the material poured so as to make a snug fit around the pipe.
3. The method claimed in claim 1:
forming openings in said mold in the area of the mold around the pipe so that some of the material leaks from said opening to fill any gap between the mold and said pipe.
4. The method claimed in claim 1:
prefabricating said mold from a pair of identical sec tions each having a concave upright section and a concave base by facing said upright concave sections and abutting said mold sections and securing same to construct the hollow :mold.
5. The method claimed in claim 1:
prefabricating said lightweight concrete mold with an open bottom having a base cavity therein and placing said mold directly on the ground so that the material is formed as a base inside said mold on the ground. 7

Claims (5)

1. In a method of making a headwall from poured material, including concrete, for a pipe inserted therein: a. prefabricating a lightweight concrete mold having walls defining an opening for the pipe inserted and an open hollow interior into which the material may be poured, said mold having a base and an upright pipe supporting portion therein in open communication to receive the poured material to form a base and upright portion in said mold from concrete, b. making openings in said mold into which the material is poured after said mold is in place, c. placing said assembled and completed mold in place in situ over the end of said pipe and pouring the material, including concrete, into said mold allowing the material to harden and providing a means for the mold to adjust to said pipe size by means of the poured material, d. then backfilling against said headwall leaving said mold permanently in place.
2. The method claimed in claim 1: fabricating said mold with deformable, solid walls around said pipe supporting portion which distorts from the material poured so as to make a snug fit around the pipe.
3. The method claimed in claim 1: forming openings in said mold in the area of the mold around the pipe so that some of the material leaks from said opening to fill any gap between the mold and said pipe.
4. The method claimed in claim 1: prefabricating said mold from a pair of identical sections each having a concave upright section and a concave base by facing said upright concave sections and abutting said mold sections and securing same to construct the hollow mold.
5. The method claimed in claim 1: prefabricating said lightweight concrete mold with an open bottom having a base cavity therein and placing said mold directly on the ground so that the material is formed as a base inside said mold on the ground.
US00212217A 1971-12-27 1971-12-27 Method of making a headwall Expired - Lifetime US3779021A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US21221771A 1971-12-27 1971-12-27

Publications (1)

Publication Number Publication Date
US3779021A true US3779021A (en) 1973-12-18

Family

ID=22790067

Family Applications (1)

Application Number Title Priority Date Filing Date
US00212217A Expired - Lifetime US3779021A (en) 1971-12-27 1971-12-27 Method of making a headwall

Country Status (1)

Country Link
US (1) US3779021A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4033383A (en) * 1974-12-23 1977-07-05 Diamond Power Specialty Corporation Thermal insulation assembly
US4723871A (en) * 1987-05-11 1988-02-09 Duane Roscoe Inexpensive headwall for culverts
US5425600A (en) * 1994-01-21 1995-06-20 Gordon; Bradford C. Drainage block feedthrough for assembly of walls constructed of specialized retaining blocks
US5536113A (en) * 1994-05-16 1996-07-16 North Star Concrete Of Ohio, Inc. Precast concrete wingwall
US5902071A (en) * 1997-07-15 1999-05-11 Bliss; Edwin C. Plastic permeable groyne system
WO2000023664A2 (en) 1998-10-21 2000-04-27 Hartman Ew, Inc. Headwall for drain pipe
US6533498B1 (en) 2000-03-20 2003-03-18 Donald S. Quin Reinforced composite material
US6644889B2 (en) 1998-10-21 2003-11-11 Hartman Ew, Inc. Headwall for drain pipe
GB2400382A (en) * 2003-04-11 2004-10-13 Steven Jeffrey Willis Apparatus and method for casting concrete headwalls
US8082753B1 (en) * 2005-10-05 2011-12-27 Patrick D. Alvarez, Jr. Beverage bead
US10731313B1 (en) 2019-07-26 2020-08-04 Homebridge Precast, LLC Retaining wall assembly

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1069650A (en) * 1912-07-08 1913-08-05 Bartholomew Scully Bank-retainer for culverts.
US1098766A (en) * 1912-09-23 1914-06-02 Bartholomew Scully Bank-retainer for culverts.
US1407246A (en) * 1920-10-05 1922-02-21 Charles F Bond Concrete mold
US2816575A (en) * 1953-05-11 1957-12-17 William S Stokes Apparatus for laying a pipe line under a right-of-way
US3045707A (en) * 1960-02-16 1962-07-24 Concrete Thermal Casings Inc Vented insulated pipe structures

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1069650A (en) * 1912-07-08 1913-08-05 Bartholomew Scully Bank-retainer for culverts.
US1098766A (en) * 1912-09-23 1914-06-02 Bartholomew Scully Bank-retainer for culverts.
US1407246A (en) * 1920-10-05 1922-02-21 Charles F Bond Concrete mold
US2816575A (en) * 1953-05-11 1957-12-17 William S Stokes Apparatus for laying a pipe line under a right-of-way
US3045707A (en) * 1960-02-16 1962-07-24 Concrete Thermal Casings Inc Vented insulated pipe structures

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4033383A (en) * 1974-12-23 1977-07-05 Diamond Power Specialty Corporation Thermal insulation assembly
US4723871A (en) * 1987-05-11 1988-02-09 Duane Roscoe Inexpensive headwall for culverts
US5425600A (en) * 1994-01-21 1995-06-20 Gordon; Bradford C. Drainage block feedthrough for assembly of walls constructed of specialized retaining blocks
US5536113A (en) * 1994-05-16 1996-07-16 North Star Concrete Of Ohio, Inc. Precast concrete wingwall
US5902071A (en) * 1997-07-15 1999-05-11 Bliss; Edwin C. Plastic permeable groyne system
WO2000023664A3 (en) * 1998-10-21 2000-07-20 Henry B Hartman Headwall for drain pipe
WO2000023664A2 (en) 1998-10-21 2000-04-27 Hartman Ew, Inc. Headwall for drain pipe
US6422788B1 (en) * 1998-10-21 2002-07-23 Hartman Ew, Inc. Headwall for drain pipe
US6644889B2 (en) 1998-10-21 2003-11-11 Hartman Ew, Inc. Headwall for drain pipe
US20040081517A1 (en) * 1998-10-21 2004-04-29 Hartman Henry B. Headwall for drain pipe
US6533498B1 (en) 2000-03-20 2003-03-18 Donald S. Quin Reinforced composite material
GB2400382A (en) * 2003-04-11 2004-10-13 Steven Jeffrey Willis Apparatus and method for casting concrete headwalls
GB2400382B (en) * 2003-04-11 2006-07-12 Steven Jeffrey Willis Apparatus and method for casting concrete headwalls
US8082753B1 (en) * 2005-10-05 2011-12-27 Patrick D. Alvarez, Jr. Beverage bead
US10731313B1 (en) 2019-07-26 2020-08-04 Homebridge Precast, LLC Retaining wall assembly

Similar Documents

Publication Publication Date Title
US3468088A (en) Wall construction
US4673157A (en) Footing form
US3779021A (en) Method of making a headwall
CA1117280A (en) Method of forming and pouring manhole bases
JP6731040B2 (en) Form insert part and wall block provided with the form insert part
US20060016150A1 (en) Paperboard formwork and method for forming concrete structures
WO1993014287A1 (en) Form for casting building elements
US1598131A (en) Method of and apparatus for constructing concrete walls
FI88952B (en) FREQUENCY FRAME FOR FORMULATION OF FORM AND FRONT CONCRETE FITTINGS
US4106743A (en) Adjustable bulkhead for concrete wall forms
CN109025265B (en) Method for supporting post-cast strip of side mold of thin plate
JPS6131261B2 (en)
EP1116829A2 (en) Foundation raft
AU656846B2 (en) Improvements in foundation construction
KR102202075B1 (en) Manufacturing method of precast concrete member
KR102485582B1 (en) Hollow type segmental prestressed concrete box girder using rubber tube mold, manufacturing method thereof, and girder manufacturing system adapted for the manufacturing method thereof
JP7275496B2 (en) Structure construction method
CN111997065A (en) Waterproof support block and mould that trades
AU634950B1 (en)
WO2000047381A1 (en) Formers and methods of casting bodies, particularly concrete bodies, using the formers
US1262652A (en) Mold for concrete structures.
JP2612076B2 (en) Centrifugal molded concrete cylinder and method of manufacturing the same
GB814302A (en) Improvements in or relating to the underpinning of buildings
EP0078276A1 (en) Coping members for liquid containers
JPH03121814A (en) Manufacture of cylinder member and cylinder member manufacture by said method